Wadworth Brewery Phase 1 and 2

ABM has completed phases 1 and 2 of the new Wadworth Brewery Upgrade.

Phase one consisted of 3 Dimensional Virtual Modelling of the existing and the proposed plant and also budget costing for the following items.

  • Civils
  • New Brewing Vessels
  • New Process Pipework and Equipment Design/Installation
  • Panel Design/ Build / Installation
  • Field Wiring Design/Installation
  • Control System Design / Build / Installation

Phase 2 of the Brewery Upgrade included the following items

  • Project Management
  • New Copper
  • New Run Off Vessel
  • New Whirlpool
  • New Heat Recovery System
  • Pipework Design/Installation
  • Automatic Routing Manifolds
  • Panel Design/ Build / Installation
  • Control System Design / Build / Installation

The total project value of this job was £2.6 million